NEC Insight: Timing Instructions & Compensation Events


NEC Insight: Should you wait for a compensation event quotation before following an instruction?

08 April 2026

A common question under NEC contracts is whether a contractor can delay carrying out an instruction until the Project Manager has formally instructed and accepted a quotation for a compensation event.

 

The short answer is No.

 

If the Project Manager issues a valid instruction, the Contractor is obligated to comply with that instruction without waiting for the commercial process to catch up. Where the instruction changes the Scope, the Project Manager should also notify it as a compensation event and instruct a quotation. However, if that administrative step has been missed, it does not entitle the Contractor to refuse or delay carrying out the instruction.

 

Understandably, Contractors may be reluctant to proceed with additional or changed Scope before the cost and time implications have been agreed, but delaying compliance can expose the Contractor to allegations that they have failed to act in accordance with the contract.  

 

What should contractors do?

 

The better approach is to:

  • Comply promptly with the instruction.
  • Keep detailed contemporaneous records of the additional cost and programme impact.
  • Notify the Project Manager if a compensation event has not been formally notified.
  • Continue to follow the contractual compensation event process while mitigating any additional cost and delay.

Practical takeaway

 

Commercial teams should treat the instruction and the compensation event process as two related but separate contractual mechanisms. An omission by the Project Manager to instruct a quotation does not remove the Contractor's obligation to comply with a valid instruction, but it should prompt an early commercial discussion to ensure entitlement is properly protected.

 

Need advice on your own project?


This article provides general guidance only and should not be relied upon as professional advice. If you're dealing with a live NEC contract issue, I'm happy to help. Arrange a free 20-minute call with me to discuss your challenge.

 

Prefer to message first? - Send me a message 

Read more Insights...

 

Scope omitted? 

Don't assume the Activity Schedule determines the deduction.

Can a Contractor make assumptions in a compensation event quotation?

"We'll sort it out later" – The most expensive words in an NEC contract

Does omitting work from the Scope bring the Completion Date forward?

Regulated by RICS

©Copyright. All rights reserved.

Information icon

We need your consent to load the translations

We use a third-party service to translate the website content that may collect data about your activity. Please review the details in the privacy policy and accept the service to view the translations.